Phases, stages, etc. A summary of the info that is also in the product, as an introduction before they get their feet wet.

Example project planThe migration to Tableau Cloud is an elaborate project in itself. While TabMove Lite will take care of the heavy lifting and perform the copy of your Tableau environment for you, you’ll still want to carefully plan when and how that copying process will take place.

Typically, we would recommend and approach that looks more or less like this:

Roadmap Planner
67ecfc1802e823d5d0bd695fd1ccddb7babf67ff601c8c6417eb993e5b574447
maplinks
timelinetrue
source%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222024-07-08%2000%3A00%3A00%22%2C%22endDate%22%3A%222024-08-31%2000%3A00%3A00%22%2C%22displayOption%22%3A%22WEEK%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22TabMove%20Lite%22%2C%22color%22%3A%7B%22lane%22%3A%22%233b7fc4%22%2C%22bar%22%3A%22%233b7fc4%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22title%22%3A%22Test%20Migration%22%2C%22description%22%3A%22This%20is%20the%20second%20bar09-02%2000%3A00%3A00%22%2C%22displayOption%22%3A%22WEEK%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22TabMove%20Lite%22%2C%22color%22%3A%7B%22lane%22%3A%22%233b7fc4%22%2C%22bar%22%3A%22%233b7fc4%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22title%22%3A%22Test%20Migration%22%2C%22description%22%3A%22Test%20migration%20-%20we%20migrate%20all%20the%20(relevant)%20content%20for%20the%20first%20time%20to%20get%20a%20feeling%20for%20how%20this%20goes.%22%2C%22startDate%22%3A%222024-07-15%2001%3A39%3A48%22%2C%22duration%22%3A1%2C%22rowIndex%22%3A0%2C%22id%22%3A%223e824093-baeb-478f-b88d-99f12efd0152%22%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222024-08-04%2022%3A20%3A11%22%2C%22id%22%3A%229b75eaaa-5414-4560-9444-65fb1f9454c5%22%2C%22title%22%3A%22Final%20Migration%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Creators%22%2C%22color%22%3A%7B%22lane%22%3A%22%238eb021%22%2C%22bar%22%3A%22%238eb021%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%22202465fb1f9454c5%22%2C%22title%22%3A%22Final%20Migration%22%2C%22description%22%3A%22We%20perform%20a%20migration%20of%20the%20content%20one%20final%20time%2C%20on%20a%20well-defined%2C%20scheduled%20date%20and%20time%20that%20were%20communication.%20This%20is%20the%20cutover%20to%20Cloud%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Creators%22%2C%22color%22%3A%7B%22lane%22%3A%22%238eb021%22%2C%22bar%22%3A%22%238eb021%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-07-22%2000%3A00%3A00%22%2C%22id%22%3A%22fee5662f-9fd3-47d7-b965-f77c9957af6a%22%2C%22title%22%3A%22Feedback%20period%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Server%22%2C%22color%22%3A%7B%22lane%22%3A%22%23f6c342%22%2C%22bar%22%3A%22%23f6c342%22%2C%22text%22%3A%22%23594300%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024f77c9957af6a%22%2C%22title%22%3A%22Feedback%20period%22%2C%22description%22%3A%22We%20involve%20Creators%20who%20own%20content%20to%20review%20whether%20their%20most%20important%20dashboards%20are%20working%20as%20expected.%22%2C%22duration%22%3A2%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Server%22%2C%22color%22%3A%7B%22lane%22%3A%22%23f6c342%22%2C%22bar%22%3A%22%23f6c342%22%2C%22text%22%3A%22%23594300%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222024-08-26%2001%3A39%3A48%22%2C%22id%22%3A%2290599942-330d-4fed-a947-54d9a34a3276%22%2C%22title%22%3A%22Decommissioning%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Cutover%22%2C%22markerDate%22%3A%22202454d9a34a3276%22%2C%22title%22%3A%22Decommissioning%22%2C%22description%22%3A%22We%20plan%20the%20decommission%20of%20Tableau%20Server%20in%20the%20future.%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Cutover%20%26%20Communication%20%234%22%2C%22markerDate%22%3A%222024-08-11%2022%3A20%3A11%22%7D%2C%7B%22markerDate%22%3A%222024-07-15%2000%3A00%3A00%22%2C%22title%22%3A%22Communication%20%231%22%7D%2C%7B%22markerDate%22%3A%222024-08-02%2022%3A05%3A56%22%2C%22title%22%3A%22Communication%20%232%22%7D%2C%7B%22markerDate%22%3A%22202402%2022%3A05%3A56%22%2C%22title%22%3A%22Communication%20%233%22%7D%2C%7B%22markerDate%22%3A%222024-08-31%2008%3A04%3A45%22%2C%22title%22%3A%22Communication%20%235%22%7D%2C%7B%22markerDate%22%3A%222024-07-31%2008%3A04%3A45%22%2C%22title%22%3A%22Communication%20%233%22%7D%5D%7D22%2000%3A00%3A00%22%2C%22title%22%3A%22Communication%20%232%22%7D%5D%7D
pagelinks
titleRoadmap%20Planner
hashcb8558a23230ab99aa780e55f32e99d0051c68165fd8c0b18ff347a411c75686

A few take aways from this example:

  • There is plenty of communication happening before, during, and after the migration.

  • TabMove is used to copy the content (at least) twice: once during a test migration, and then once again during the “final migration”. Note that the copying of the content is unlikely to take a full week like the example suggests, but rather a few hours. Nonetheless, planning enough time to experiment with TabMove and perform a few tests may be a good idea.

  • After the content has been copied during the first test migration, a feedback period for Creators is organized. They are invited to actively access and review their content that was copied to Tableau Cloud, and provide feedback. Tweaks and fixes can be applied as lessons learned in preparation of the final migration.

  • The final migration is planned well ahead of time and will serve as the cutover after which Tableau Server is no longer accessed. The results of this final copy with TabMove are predictable thanks to previous iterative testing.

  • The decommissioning of Tableau Server is planned in the future, as a further incentive to fully transition operations to Tableau Cloud. Accesses for Viewers, Explorers and Creators who aren’t administrators can be taken away soon after the final migration.

Of course, the actual durations of these phases may vary based on company processes, requirements and other circumstances.